Project menu
Set Baseline — Set a baseline schedule for the project, or for just the selected tasks.
Delete Baseline — Delete the currently selected baseline schedule for the project.
Track Changes — Summons the Change Tracking view which allows you to see who has changed something in the project.
Automatically Level Resources — Have OmniPlan dynamically adjust resources to fit new changes as aspects of the project are modified, or new load information is received from other projects. Enabled by default when you create a new project.
Clear Leveling — Get rid of all resource-availability dependencies and let tasks be scheduled based only on constraints and prerequisites.
Set Current Editing Date — Once you set this date, all newly created tasks will start on the current editing date.
Set as Default for New Tasks — Assimilates all of the attributes from a selected task, using it as the default template for new tasks in the current project. Resistance is futile.
Configure Publishing & Subscriptions — Open the Publishing & Subscriptions window, where you can set up all of your automated collaboration and export actions.
Publish — Pushes your project data out to your collaboration servers.
Update — Synchronizes all the new changes from your collaboration servers into your project.